Well, I have really done it now.  I have a major assignment for work in the middle of October, so my poor IDers and contractor will have to speed up stuff for the house.  I think it is going to be really tight…sure hope it pulls through.  fingers crossed.

 

27/28 Sept – As of now…carpentry is still being fabricated for the kitchen, pathway to the living room and for the master bedroom wardrobe.  Installation is scheduled to begin on either 27 or 28 Sept.

 

2 Oct – Carpentry installation is scheduled to wrap up on 2 Oct.  On that same day, granite which is from a different vendor,will be coming in to take measurement for the granite (kitchen counters..many many counters..LOL, bathroom counter) on 2 Oct.

 

5 Oct – EziLiving Clothes Drying System Installation, Internet and phone line installation

 

6 Oct – Sign up and collect Starhub cable box

 

7 Oct – Our new sofas, dining set, fridge, freezer, washing machine, wine fridge, king bed and mattress, curtain installation all to be delivered.

 

9 Oct – Installation of granite hopefully, movers bringing stuff from the old home to new home.  Plan to spend first night in the new home and start unpacking

 

Boy oh boy..it is going to be tight..fingers crossed everything works out!